Here's an update from Street Superintendent Rodney Jacobs on the street work. 

The Street Department will be chip sealing Osage Street and Pheasant Road on Wednesday starting at 8:00 am. 

Osage will be sealed first and Pheasant following. Sweeping will be performed on both streets prior to sealing and Brookridge will be swept of any loose gravel as well. 

The micro-surfacing and slurry sealing by contractors is now scheduled to began on Monday July 24th. It is expected to take about a week to complete.

The milling of asphalt and overlay is scheduled to began on August 7th. It is expected to take about a week to complete.