That’s when work begins on replacing the deteriorating structure.
Once the bridge is closed, crews will have 95 calendar days to build the new bridge and open it to traffic.
Signs and electronic message boards will alert drivers to the bridge closing.
There will be no signed detour. Drivers are urged to find alternate routes around the work zone.
The existing bridge was built in 1959 and is experiencing increasing deterioration. Approximately 300 vehicles cross the bridge daily.
The new bridge will be wider and slightly longer than the existing structure.
Weather and/or scheduling conflicts could alter the work schedule.
Project background:
Prime Contractor: Boone Construction Co., Columbia
Completion Date: Aug. 15, 2018 (Contractor expects to complete the project by late June)
Total Project Cost: $1.01 million